STAGE 3
%
Civil Construction
​
Registration status
100%
Compliancing
​
STAGE 4
%
Civil Construction
Site Establishment
Bulk Earthworks
Drainage Works
Sewer Works
Water & Gas Reticulation
​
Conduit and AGI Installation
Pavement Works
​
Kerb & Channeling
Electrical & NBN
Footpaths & Top Soiling
Asphalting and Line-marking
90%
​
100%
​
100%
​
100%
​
100%
​
100%
80%
​
100%
85%
​
65%
0%
STAGE 5A
%
Civil Construction
​
Registration status
100%
Compliancing
STAGE 5B
%
Civil Construction
Site Establishment
Bulk Earthworks
Drainage Works
Sewer Works
Water & Gas Reticulation
​
Conduit and AGI Installation
Pavement Works
​
Kerb & Channeling
Electrical & NBN
Footpaths & Top Soiling
Asphalting and Line-marking
60%
80%
​
95%
​
95%
​
100%
​
100%
​
80%
​
55%
0%
0%
0%
STAGE 6
%
Civil Construction
Site Establishment
Bulk Earthworks
Drainage Works
Sewer Works
Water & Gas Reticulation
​
Conduit and AGI Installation
Pavement Works
​
Kerb & Channeling
Electrical & NBN
Footpaths & Top Soiling
Asphalting and Line-marking
80%
​
90%
​
100%
​
100%
​
100%
​
100%
​
80%
​
100%
​
50%
​
60%
​
0%